Sherley Farms developer would be repaid from the subdivision's own impact fees under a deal set for Nov. 17

A consent item would let Tellus Texas III recover the cost of water, sewer, road and drainage work through impact fees collected inside the 1,100-acre project, and would set aside up to four acres for a future fire station.

Demarcus Ramos· AI-assisted, edited by Jake Team

November 11, 20262 min read

Sherley Farms Development - illustration, Jake Team LLC

Impact fees paid by home builders inside Sherley Farms would go into a separate city account and flow back to the subdivision's developer under an economic development agreement on the Anna City Council's consent agenda for Tuesday, Nov. 17.

The agreement with Tellus Texas III, LLC, posted with the agenda Tuesday, sets up a grant under Chapter 380 of the Texas Local Government Code.

It builds on a development agreement the city, the developer and Sherley Partners, Ltd. signed in December 2024 for the mixed-use project, which the documents say will include single-family homes of various sizes, townhomes, apartments and commercial space built in phases.

How the money would move

Under the draft, the city would collect impact fees on every building permit in Sherley Farms and park them in a "Sherley Farms Impact Fee Account." Once the developer finishes and documents eligible infrastructure, the city would pay it back each quarter from that account, up to whatever balance is available.

The eligible work listed in the agreement is the major water, sewer and roadway improvements shown in an exhibit, plus the land for an elevated water storage tank. The total the developer could receive is capped at the actual cost of that work, minus anything paid for with public improvement district bonds.

The draft says no cost can be reimbursed twice and that the city never has to pay more than the cap, even if fees collected in the project run higher. Once the cap is reached, the city could use later impact fees from the development for any lawful purpose.

The agreement does not put a dollar figure on the infrastructure. The developer would submit certified cost statements, which the city manager or city engineer would have to approve before any payment.

Fire station site

The draft also records a change to the original deal: the city has decided to build a fire station at the water tower site. That enlarges the land the developer must convey to three contiguous acres, plus up to one more acre for the fire department, for a total of up to four acres. The extra land counts as reimbursable infrastructure.

The developer would have to dedicate that site, along with right-of-way the Texas Department of Transportation is expected to require next to it, by May 31, 2027. Any money the city receives for that right-of-way would be passed to the developer within 30 business days.

The property

Legal descriptions attached to the agreement cover two tracts: about 970 acres starting on the north line of FM 455 and about 153 acres starting on the north line of FM 2862. A council resolution would also direct staff to post the agreement online, as state law requires for Chapter 380 deals.

Consent items are usually approved together in one vote unless a council member asks to discuss one separately. Council members convene at 6 p.m. in the Anna Municipal Complex, 120 W. Seventh St.

Sources

annatx.api.civicclerk.com

annatx.api.civicclerk.com